Tanzania: Verdensbanken kompenserer landsbyboere med solpaneler

Hedebølge i Californien. Verdens klimakrise har enorme sundhedsmæssige konsekvenser. Alligevel samtænkes Danmarks globale klima- og sundhedsindsats i alt for ringe grad, mener tre  debattører.


Foto: Kevin Carter/Getty Images
Redaktionen

The Tanzanian government and the World Bank have devised a means of exploiting the countrys natural gas resources to increase the countrys much needed electrification.

A private international consortium, Songas, has built a 200-km underground pipeline at a cost of 295 million US dollar to carry natural gas from the island of Songo Songo to the industrial area of Ubungo in the huge East African countrys commercial centre, Dar es Salaam.

A gas power plant in Ubungo began operating on 21 June. By the end of the year it will generate 120 megawatts of electricity, roughly one quarter of Tanzanias current peak demand.

The electricity will be a huge boost to metropolitan areas, but most Tanzanians live in rural areas. Less then 1 percent have electricity and the added power from the pipeline will not go to them.

In constructing the pipeline, around 100.000 people living in 25 villages and four towns along the Songo Songo pipeline had their land dug up and their lives disrupted.

Compensating them by extending the grid to their homes using conventional transmission wires from a central power plant would cost approximately 10.000 US dollar per kilometre, according to a 2004 report by the UN Development Programme (UNDP). Instead, the government and the World Bank have devised the wayleave village electrification scheme.

The scheme includes building a miniature, 4.5-megawatt, power station approximately 200 km south of Dar es Salaam, with an electric grid that would supply electricity to some 80.000 people living in four towns.

For the remaining 20.000 people in the 25 villages, providing electricity from the mini-grid would be too expensive. But each household would get solar panels.

The World Bank is funding both the mini-grid and the solar panels project, which will cost an estimated 10,6 million US dollar that is just 3 percent of the cost of the Songo Songo pipeline.

But so far the wayleave project is just in a starting phase. It has been two years in the making and was supposed to have been completed along with the pipeline on 21 June.

– Nothing has actually been put in the ground, said Norbert Kahyoza, a senior planning engineer at the Tanzanian Ministry of Energy and Minerals.

He could not say when the scheme would be completed but expected it to happen before 31 March 2006, which is when credit from the World Bank will run out.

The problem is that the original scheme had to be revised radically. The first plan was for the towns along the pipeline to access the gas by creating a series of power stations. That turned out to be expensive and impractical, Kahyoza said.

The current type of mini-grid scheme is now favoured in many developing countries. They are a “lowest-cost means of providing electricity to neighbourhoods or entire communities,” according to a World Bank report.

But the grids are often improvised. The locals who run them are often inexperienced. The grids are inefficient, unsafe and short-lived.

The Tanzanian government has promised that the wayleave mini-grid will be different. The government has started hiring professional contractors to build and manage the project so that the power is reliable and safe.

This would be a boost to local industry and commerce in the four towns.

Kilde: FN-bureauet IRINnews